Kiama Council Retirement Village Faces Unit Sales Shortfall

Kiama Council’s retirement village at Terralong has a budget problem that comes down to one thing: apartments that cannot be sold until fire safety work is finished. According to The Weekly SOURCE’s report on the council’s November budget review, the delay is now showing up in the numbers.

What the budget review forecasts

Blue Haven Terralong is a 203-unit retirement village on the NSW South Coast. The council’s November budget review, presented on 17 November, forecasts that revenue from independent living unit sales will come in $1.849 million lower than planned.

The Weekly SOURCE reported that the cause is the delay to fire safety rectification works at Stage 5. Those works have to be completed before the affected apartments can be sold, so the units sit empty and bring in nothing in the meantime.

The same review proposes cutting capital spending at the village by about $3.7 million in this financial year. Most of that is a deferral of $3.297 million in refurbishment and asset-condition works. The council wants to hold that money until an independent third-party review is done.

A further $400,000 has come out of the budget after the fire safety tender result. Some of the remaining spending has been pushed into 2027-28, because the works will start later than first planned.

The longer maintenance bill

The figures sit against a much larger backdrop. The Weekly SOURCE reported in October that an independent assessment found the village needs $51.2 million of maintenance over 10 years to lift its condition from poor to average.

That sum makes the deferral of refurbishment spending more notable. Work that the assessment says is needed is being held back while the council waits on a further review, and the Stage 5 fire safety upgrades are not expected to finish until mid-2028.

For residents, the council has previously confirmed that people can stay in their homes during the works. Where it is necessary, residents will be temporarily moved to other places within the village.

Questions from councillors

Councillor Yasmin Tatrai has asked the council for detailed information on several points: vacant apartments, refurbishment spending, refunds to residents and management accountability. Chief Executive Officer Jane Frawley advised that the answers would be given at the council’s December meeting.

The Weekly SOURCE also reported that the NSW Government has required the council to prepare an independent business case on the future of Terralong. The options to be examined are keeping the village, leasing it, entering a partnership, or selling it.

The council has already sold one of its Blue Haven facilities. In April 2025 it sold the separate Blue Haven Bonaira aged care home, together with 59 independent living units, to Hall & Prior.

What this means in practice

A retirement village that sells independent living units depends on those sales for part of its income. When a block of apartments is held off the market, as Stage 5 is, the revenue does not arrive, and a council running the village has to adjust its budget around the gap.

Fire safety works are not optional extras, which is why the sales cannot go ahead first. The result is a sequence in which compliance work comes first, then sales, and the money from sales supports later spending. A late start to the first step pushes back the rest.

The numbers in the review show how that sequence plays out. The $1.849 million sales shortfall is money the council expected to receive this financial year. The $3.7 million reduction in capital spending is money it now does not expect to spend this year. Part of that reduction is a straight deferral, which means the work is delayed rather than cancelled. The $400,000 taken out after the tender outcome and the amounts moved into 2027-28 are tied to the later start on the fire safety works.

It is worth reading the two figures side by side. The sales shortfall is smaller than the spending reduction, but they come from the same cause and affect the same village. Selling fewer units means less income, and holding back refurbishment means the condition of the buildings is not being lifted while the review is under way. The independent assessment described the village as being in poor condition, so a pause in refurbishment is a pause in work the assessment says is needed.

For ratepayers in the Kiama area, the questions are about how much the village will cost the council and whether it should keep running it. Those are the questions the business case is meant to address, and the answers to Councillor Tatrai’s questions in December will add detail on vacancies, refunds and spending.

For current and prospective residents, the figures raise practical points. Stage 5 will not be finished for some time, refurbishment money has been put on hold, and the village’s ownership could change depending on what the business case recommends. The reporting does not say what any decision would mean for existing residents, and none appears to have been made.

People who already live at Terralong have one firm piece of information from the council: they can stay during the works, with temporary moves inside the village if the work requires it. Anyone considering buying into the village will want to note that the affected Stage 5 apartments cannot be sold until the fire safety rectification is complete, and that the upgrades are not expected to be finished until mid-2028.

The immediate dates are the council’s December meeting, where the answers are due, and mid-2028, when the Stage 5 fire safety upgrades are expected to be finished.

About the author

Tessa Delgado starts any new piece by reading primary sources, comparing how several providers describe their services, and checking each claim against independent material. She writes about electric vehicle charger installation, funeral services and two factor authentication. She lives in Denver and restores old furniture.